A method to planning sales
Summary
-
copy history
- start with open orders
- add orders as placed in past
- true-up to current run rate
- normalize price for current pricing
- will need to idenitfy blocks in the base period that best represent pricing efforts
- scale prior periods to match final pricing
- exclude expired products/customers
- scale new developments to reflect full-year (new products customers)
- update cost to current
- request date attainment performance
- normalize price for current pricing
- true-up to current run rate
- walk prior period sales to new baseline sales as change in run-rate
-
build in changes to current run-rate
- volume changes
- pricing changes
- new products (must be defined in future at a mininum)
- future cost changes
- request date attainment
timeline | day | running days | responsible |
---|---|---|---|
establish run-rate sales | |||
copy history | 1 | 1 | executor |
identify pricing windows | 1 | 2 | sales team |
scale windows to match final | 1 | 3 | executor |
identify expired products/customers | 3 | 6 | sales team |
eliminate expired volume | 1 | 7 | executor |
identify new products/customers | 3 | 10 | sales team |
scale new to full year volume | 1 | 11 | executor |
load new plans | |||
layer in planned changes not yet implemented | |||
identify changes to existing volume | 3 | 14 | sales team |
load changes | 1 | 15 | executor |
identify changes in price | 3 | 18 | sales team |
load changes | 1 | 19 | executor |
identify new products | 3 | 22 | sales team |
load new | 1 | 23 | executor |