Logic to setup production plan, inventory balances, purchases, and shipments
Starting point
- known balances STKB
- known available BOLH - not posted
- known prod schedule SOFT
- known shipments Sales Forecast
- forecasted orders Sales Forecast
- machines that a part can run on ??
- actual run-time performance Alternates
- actual BOM performance Alternates
- actual scrap performance Alternates
- available machine time ??
2017-09-28 12:16:23 -04:00
Populate
- forecasted prod schedule
- forecasted on-hand (via forecast perpetual transactions)
- forecasted available (via forecast transactions)
2017-09-28 12:16:23 -04:00
- forecasted purchases
Iterate through each calendar day
1. materialize forecasted purchases
1. update on-hand & available
2017-09-28 12:16:23 -04:00
2. materialize production
1. update on-hand & available
3. materialize transfers
1. update on-hand & available
2017-09-28 12:16:23 -04:00
3. materialize shipments
1. update on-hand & available
2017-09-28 12:16:23 -04:00
4. process forecasted order submissions
1. check for inventory available
1. Yes
1. mark unavailable
2. schedule shipment for request date
2017-09-28 12:16:23 -04:00
2. No or partial
1. mark unavailable any partial
2. schedule on next open slot regardless of request date (each part should be mapped to certain set of machines)
2017-09-28 12:16:23 -04:00
1. raw materials available
1. Yes
1. mark unavailable (at begin prod date?)
2. No
1. mark unavailable any partial (at begin prod date?)
2. schedule a purchase net of lead time
2. sub-components available?
1. Yes
1. mark unavialable (at begin prod date?)
2. No
1. (return to 4.1.2.2)
3. schedule transfer of production after completion if necessary
3. schedule shipment for request date, or production date if past request date
snap-shot STKB
snap-shot BOLH
snap-shot SOFT