2.0 KiB
2.0 KiB
worked on so far
setup
the basic assumption is a single sales table is available to work with that has a lot of related data that came from master data tables originally. the goal then is to break that back apart to whatever degree is necessary.
- run
schema.sql
andperd.sql
to setup basic tables - create a table fc.live as copied from target (will need to have columns
version
anditer
added if not existing) - run
target_info.sql
to populate thefc.target_meta
table that holds all the columns and their roles - fill in flags on table
fc.target_meta
to show how the data is related - run
build_master_tables.sql
to generate foreign key based master data
routes
- all routes would be tied to an underlying sql that builds the incremental rows
- that piece of sql will have to be build based on the particular sales layout
- columns: a function to build the columns for each route
- where a function to build the where clause will be required for each route
- the result of above will get piped into a master function that build the final sql
- the master function will need to be called to build the sql statements into files of the project
route baseline
- forecast = baseline (copied verbatim from actuals and increment the dates) + diffs. if orders are canceled this will show up as differ to baseline
- regular updates to baseline may be required to keep up with canceled/altered orders
- copy some period of actual sales and increment all the dates to serve as a baseline forecast